Masterplan

Masterplan 2008

3 phases:

  • Phase 1 (Boarding House and Music Department) - Completed
  • Phase 2 (Main House Sixth Form Centre) - About to start
  • Phase 3 (Swimming Pool) - Moved to Phase 2a owing to January 2014 fire

Masterplan 2016

  • A very ambitious project spanning the next decade
  • Sectioned into discreet phases so that if funding is under pressure we can stop and restart when funds are available

For further information, have a look at the designs of our architects, Hawkins\Brown, below.

You have not allowed cookies and this content may contain cookies.

If you would like to view this content please

  • Temporary Dining and Catering 2017-2018

  • Main House works and Medical Centre 2017-2019

  • Remodel Stable Block for new Library / Learning resources Centre and demolish Philp House 2019-2020

  • New Junior School and Entrance Works including new reception lodge 2019-2021

  • Demolish old Junior School 2021-2022

  • New Dining and Catering. Extend Boarding 2020-2023

  • Demolish existing Assembly Hall 2023

  • New (larger) Assembly Hall 2023-2024